TECO Line Streetcar System Whiting Street Extension Project

 

Streetcar Extension Maintenance of Traffic (MOT) and Construction Activities for
Wednesday 12/9/09 through Monday 12/14/09

   

Wednesday 12/9/09

MOT
· Channelside – Two eastbound lanes closed on south side – third lane on Channelside open at 4pm

· Franklin – Northbound closed from Old Water to Brorein

Construction
· Installation of storm sewer east of the Franklin/Channelside intersection within Channelside

Thursday 12/10/09

MOT
· Channelside - 6:30am – Close two eastbound lanes on the north side – third lane on Channelside open at 4pm

· Franklin St - Northbound closed from Old Water to Brorein

Construction
· Installation of storm sewer and water main within Channelside/Franklin intersection

Friday 12/11/09

MOT
· Channelside – Close two eastbound lanes on the north side – third lane open from 4pm till 8pm. Second lane closed from 8pm till 2am. Third lane closed from 2am to 4am Saturday morning.

· Franklin St - Northbound closed from Old Water to Brorein

Construction

Day Crew - 7:00 am to 3:30 pm
· Installation of storm sewer and water main within Channelside/Franklin intersection

Night Crew - 9:00 pm (Friday) to 6:00 am (Saturday)
· Storm sewer within Channelside

Saturday 12/12/09
MOT
· Channelside – Close two eastbound lanes on the north side

· Franklin St - Northbound closed from Old Water to Brorein

Construction
· Water main installation and begin road base and asphalt work.

Monday 12 /14/09

MOT
· Channelside – Close two eastbound lanes on the north side – Remove all MOT at 4pm.

· Franklin St - Northbound closed from Old Water to Brorein – Remove all MOT at 4pm.

Construction
· Complete storm sewer and asphalt work

Monday 12/14/09 - 4pm – Remove all MOT and open all lanes of traffic in all directions

 
 
     
 